Licensing & Permitting
The Chamber is committed to assisting your company and industry by providing all the licensing and permitting information you may need to grow your business.
Inspection Department
Building Permit
- Each Sub needs a permit (Mechanical, Electrical, Plumbing, Gas). These are included in overall Building Permit process
- 15 days for initial Design Review
- 3 to 4 weeks for approval
- Permit fee is Total Construction Amount x .0055
Engineering Department
Site & Grading Permit
- Civil drawings routed to Traffic Engineering, then Zoning, then the Engineering Department
- No fee for the Site & Grading Permit
- 1 week for approval
- A Sewer Tap Fee of $1,000 is required unless the company is having the sewer extended
Natural Resources & Environmental Management
Permit Process:
- Air Permit
- 60-120 days
- Fee based on level of review (Chapter 3 of Huntsville Air Pollution Control Regulations)
Alabama Department of Environmental Management
Permit Process:
- Sewer Discharge Permit 60-90 days
- Storm Water Discharge Permit 60-90 days
- Hazardous Waste Generator ID 15-30 days
- Fees based on level of review